Sheehan Hall East Elevation Tuck Pointing and Window Replacement

Continuing the work started in Summer 2012, Sheehan Hall will undergo another summer construction season to complete tuck pointing and window replacement on the east elevation of the building.  This will include full tuck pointing, masonry shelf angle and lintel repair and replacement, selective brick replacement and cleaning of the entire wall.  The windows in each resident room from the 2nd level up will be replaced with new aluminum framed windows to improve safety and energy efficiency.  Some on-grade work will also be completed including the removal and replacement of the wood deck and a new concrete sidewalk.

Major demolition and construction work is scheduled to begin on May 13, 2013, and be completed by August 9, 2013.  The on grade work will be completed by September 27, 2013.

Design Team:  Inspec, Inc.

General Contractor:  Sheehy Construction Company