Kryzsko Project Schedule

A high level look at the overall project schedule includes the following milestone dates:

 September 2013     Start of on-site construction 
 Mid-December thru Mid-January 2014     Work in the occupied office areas 
 December 2013                     Work in the Winonan Room
 February 2014 Work in the Bookstore 
 June 2014     Substantial completion and Owner occupancy
 July 2014                 Final completion 

The General Contractor is responsible to provide WSU with an updated project schedule every month.  This schedule is a living document and will change and fluctuate depending on a number of variables such as weather, unforeseen conditions and speed of work.  This project schedule is highly detailed, including time duration for specific construction processes.  Check back monthly for a schedule update.